In early December 2017, Zugo Testing was approved by the leading experts of the power supply bureau for analyzing the abnormal causes of cable circulation and the location of outer sheath faults on 110 kV Gaohai River Line and 110 kV Longguang I and II Lines in Qinzhou City, Guangxi Province.
Pre-work
team meeting, safety confession
During
Dec 4th,2017 to Dec 5th, 2017, the whole line of 110kV
Gaohaijiang circuit was overhauled. After testing, technicians from Zugo
located to two fault locations. One is discharge breakdown which was repaired
and tested up to standard.
During
Dec 8th,2017 to Dec 14th, 2017, the whole line of 110kV Longguang I and II circuit
was overhauled. After testing, technicians from Zugo located to two fault located on the outer sheath of cable. After on-site
inspection and treatment by technicians, the circulation of Longguang Ⅰ&Ⅱ line has been obviously lowered.
With
the acceleration of the pace of social and economic construction, the demand
for power in industrial , agricultural production and people's daily use are
increasing. Thus the requirements for the safe operation of the power grid are higher.
As a professional third-party testing platform, Zugo Testing will unswervingly
provide rigorous and imparcial testing services for the reliable operation of
power cables. We take customer safety as our responsibility!